Canyon Watershed Restoration Project — Weekly Update

The Past Week

  • Left Hand Excavating completed pre-construction prep at Reach 1.
  • Western States continued to work on securing plant materials.
  • Civil Arts completed staking grading limits at Reaches 7 and 9 and began on construction staking throughout Reach 1.
  • Our staff worked with Biohabitats and CU to complete vegetation surveys.

A Look Ahead

  • Construction (bank grading and in-stream) work is starting at lower end of Reach 1 on Tuesday and Boulder County staff will be on-site to help with cultural assessments. This should take about one week.
  • Construction in the middle and upper portions of Reach 1 will begin the following week, Sep 9.
  • A second construction crew is planning to start work at Reach 9 on September 16.
  • Deb and Glenn will be visiting sites to complete photomonitoring.
  • Civil Arts will continue construction staking at Reach 1 and work upstream (starting at Reach 9 then returning to Reach 2) in the coming weeks.
  • Utility Locators will continue visiting sites, starting at Reach 9 then returning to Reach 2, in the coming weeks.
  • Final construction walk throughs will continue for Reaches 4-9. Thanks again for your responsiveness and flexibility as I reach out to schedule these.

As always, please let me know if you have any questions.

Best,

Yana