Canyon Watershed Restoration Project — Weekly Update

The Past Week

  • Construction began at the lower end of Reach 1. Work focused on overflow channel excavation.
  • Funders visited sites to assess progress and provide feedback.
  • Western States finalized the plant materials list.
  • Civil Arts continued construction staking throughout Reach 1.
  • Our staff completed pre-project photo-monitoring at sites.

A Look Ahead

  • Construction (excavation and in-stream) work will continue at Reach 1, moving upstream.
  • A second crew will begin at Reach 9 the week of September 16, after a final site visit with Boulder County for our Stormwater Permit.
  • Deb and Glenn will be visiting sites to complete photomonitoring.
  • Civil Arts will continue staking grading limits in the upper reaches prior to final landowner walkthroughs.
  • Utility Locators will continue visiting sites in the coming weeks.
  • Final construction walk throughs will continue for Reaches 4-9. Thanks again for your responsiveness and flexibility as I reach out to schedule these.

As always, please let me know if you have any questions.

Best,

Yana