Canyon 10/2/19

Canyon 10/2/19

Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued point bar grading in the middle stretch of Reach 1. (Crew 1) Construction is finishing up at Reach 7 at the end of this week. Work included bench grading, removing...
Canyon 9/26/2019

Canyon 9/26/2019

Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued at the lower end of Reach 1. Work included bench and point bar grading at the downstream end. (Crew 1) Construction finished up Reach 9. Work included bench grading and...
Canyon 9/19/2019

Canyon 9/19/2019

Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued at the lower end of Reach 1. Crew 1 completed overflow channel grading and added pool habitat in several locations. Crew 1 also started bench and point bar grading further...
Canyon 9/6/2019

Canyon 9/6/2019

Canyon Watershed Restoration Project — Weekly Update The Past Week Construction began at the lower end of Reach 1. Work focused on overflow channel excavation. Funders visited sites to assess progress and provide feedback. Western States finalized...
Canyon 8/30/2019

Canyon 8/30/2019

Canyon Watershed Restoration Project — Weekly Update The Past Week Left Hand Excavating completed pre-construction prep at Reach 1. Western States continued to work on securing plant materials. Civil Arts completed staking grading limits at Reaches 7 and 9 and...
Canyon 8/26/2019

Canyon 8/26/2019

Canyon Watershed Restoration Project — Weekly Update The Past Week Left Hand Excavating began pre-construction prep at Reach 1. Western States continued to work on securing plant materials. Civil Arts continued to work on staking grading limits at Reaches 7 and...