Canyon, Weekly Updates
Canyon Watershed Restoration Project — Weekly Update The Past Week Construction wrapped up at all reaches and equipment was removed from the sites. Planting and willow staking wrapped up until the spring. Erosion control blanket (and seed at these locations) was...
Canyon, Weekly Updates
Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued in the main channel and around the fish passage area. (Crew 1) Construction wrapped up at Reach 2. (Crew 2) Planting and willow staking wrapped up until the spring. A Look...
Canyon, Weekly Updates
Canyon Watershed Restoration Project — Weekly Update The Past Week Construction wrapped up in the middle stretch of Reach 1 and the crew started work in the main channel and the fish passage area. (Crew 1) Construction continued Reach 2 after mechanical issues...
Canyon, Weekly Updates
Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued in the middle stretch of Reach 1. Construction was shut down due to heavy snow and cold weather for parts of the week. Work focused in the central part of the project area,...
Canyon, Weekly Updates
Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued in the middle stretch of Reach 1. Work focused completing the pond area. (Crew 1) Construction wrapped up at Reaches 4 and 5, and started at Reach 2. Work focused on bench...
Canyon, Weekly Updates
Canyon Watershed Restoration Project — Weekly Update The Past Week Construction continued in the middle stretch of Reach 1. Work focused on excavating the pond area. (Crew 1) Construction continued Reach 5. Work focused on bench grading, removing sediment, and...